Burchell Reserve Upgrade

The Burchell Reserve Upgrade – which includes new tennis courts, play equipment, toilets and picnic facilities – will create the ideal place to gather with family and friends and participate in recreation activities.

Overview

Google Map of Burchell Reserve, St Peters SA

Estimated cost: $2.6 million

The Burchell Reserve Upgrade will establish a contemporary park setting, ensuring that residents and the wider community have great recreation facilities well into the future. Anticipated benefits of this project include:

  • high quality and well-maintained open space and recreation facilities
  • increased community participation in recreation activities
  • improved public accessibility and safety
  • reduced flood risks for City residents.

Project details

The Burchell Reserve Upgrade includes:

  • a multi-purpose court featuring two community tennis courts, basketball and netball rings
  • new toilets, shelter, barbeque and picnic facilities
  • new play equipment, furniture, lighting and fencing
  • ramp access to and from Sixth Avenue and internal paths
  • new landscaping and irrigation
  • on-site stormwater detention, cleaning and reuse.

Download Burchell Reserve Master Plan:

Burchell Reserve Master Plan

Burchell Reserve Upgrade Timeline

  • June 2021

    Completed

    Master Plan endorsed by Council

  • November 2021

    Completed

    Design consultants appointed

  • December 2021

    In progress

    Detailed design

  • Winter 2022

    Scheduled

    Construction tender

  • Spring 2022

    Scheduled

    Contractor appointed and construction works commence

  • 2023

    Scheduled

    Construction works complete

Project management

City of Norwood Payneham & St Peters

Design

  • Landscape Architecture - Outerspace
  • Civil & Structural Engineering – FMG
  • Electrical & Hydraulic Services Engineering – Trinamic

Contractor

To be confirmed