Skip to Content

Third Creek Drainage Upgrade: Stage 2

Upgrades to Third Creek will be carried out over several stages with the first stage now complete.

Overview

Project cost: $650,000

The Third Creek Drainage Upgrade Project forms part of a $38.4 million program to upgrade the City’s stormwater drainage network over the next 15 years.

The upgrade will benefit the community by:

  • addressing and reducing the impacts of flooding
  • helping to protect residents, their homes and property
  • protecting the City’s assets such as footpaths, kerbing and street trees.

Background

The City’s stormwater drainage network is one of many infrastructure assets which is provided and maintained by the Council for the community. The network removes surface water from roadways and provides appropriate levels of flood protection throughout the City.

The City-wide upgrades to the stormwater drainage network follows a floodplain mapping project which identified locations at risk of flooding and considers a range of future scenarios that could influence this including infill development and expected climate change.

Stage 1 of the Upgrade, completed in August 2020, increased capacity of Third Creek from Bridge Road to Payneham Road, Payneham, which also included the former Schweppes site at 382 Payneham Road, Payneham.

Project details

The Third Creek Drainage Upgrade Project: Stage 2 will increase the capacity of Third Creek from Bridge Road to Payneham Road, Payneham.

Works include:

  • construction of new concrete base and walls from Henry Street to Bridge Road
  • increased catchment area between Henry Street and Bridge Road
  • construction of new concrete culverts under Bridge Road
  • increased flow path under Bridge Road
  • relocation of services along Bridge Road.

Third Creek Upgrade: Stage 2 timeline

  • December 2019

    Completed

    Endorsed by Council

  • January 2021

    Completed

    Construction commenced

  • February 2021

    In progress

    Major construction works including relocation of water main, installation of reinforced concrete box culverts and installation of stormwater pipes

  • March 2021

    Scheduled

    Laying of concrete kerbing and road asphalt, reinstatement of driveways and fencing.

  • March 2021

    Scheduled

    Project completion

Project management

City of Norwood Payneham & St Peters

Design

Tonkin Consulting

Main contractor

Beltrame Civil Operations Pty Ltd

Subcontractors

WS Concrete

Council contact

For further information regarding this project, please contact the Council’s Project Manager – Civil, Rico Palombella on 08 8366 4559 or email rpalombella@npsp.sa.gov.au