Timeline
-
Endorsed by Council
September 2019Complete
-
Construction commenced
February 2020Complete
-
Installation of 145 metres of 3.6 x 1.8 metre reinforced concrete box culverts (large concrete drains) along Ashbrook Avenue, Payneham
March–May 2020Complete
-
Installation of 35 metres of reinforced concrete box culverts along Ashbrook Avenue, Payneham
May 2020Complete
-
Relocation of water main on Ashbrook Avenue, Payneham Installation of stormwater pipes along Lewis Road, and Ashbrook Avenue, Payneham
May–July 2020Complete
-
Laying of concrete kerbing along Ashbrook Avenue and Lewis Road, Payneham
July 2020Complete
-
Re-laying of asphalt along Ashbrook Avenue and Lewis Road, Payneham
July–August 2020Complete
-
Project Completed
August 2020Complete