Payneham Memorial Swimming Centre Upgrade

Payneham Memorial Swimming Centre Upgrade

Media gallery

Category: Venues and facilities

Plans are well underway to transform the Payneham Memorial Swimming Centre into a state-of-the-art aquatic facility.

Work is expected to start in September 2023, with the new Centre reopening in 2024.

The Council has allocated a budget of $24 million to deliver the project, which includes a $5.6 million Local Government Infrastructure Partnership Program contribution from the State Government.

Watch update from Mayor Bria:

 Project details

A full design team consisting of architects and engineers has been engaged during the past year and undertaken a considerable amount of design work.

The following outcomes have been achieved to date:

  • 95% completion of detailed design and documentation
  • planning approval and;
  • five local building companies have been selected to tender for the works.

It is the Council’s intention to tender the building works package by mid 2023. Based on this timeframe, it is anticipated that a contractor will be appointed and ready to commence construction in September this year.

The Council appreciates the community's understanding and patience while the Payneham Memorial Swimming Centre is closed for redevelopment.

The Payneham Memorial Swimming Centre Upgrade will include:

  • an 8 lane, 25 metre indoor pool
  • an 11 x 20 metre indoor learner’s pool
  • a 10 lane, 50 metre outdoor pool
  • a 14 metre tall tower with two waterslides
  • a zero-depth waterplay area
  • multiple male, female and unisex all-access changerooms with showers, toilets and lockers
  • multipurpose meeting room
  • shade shelters, picnic seating and barbeques.

Each pool will have an all-access entry via ramp or lift. Aquatic wheelchairs will be available for public use.

Site Address

194 OG Rd, Felixstow SA 5070

Cost

$24,000,000

Project Contact

Contact Jared Barnes

Contact role Project Manager, Urban Design and Special Projects

Phone 08 8366 4506

Email jbarnes@npsp.sa.gov.au

Subscribe to receive updates on our Major projects

Subscribe

Timeline

  • Concept design endorsed by Council

    3 May 2021

    Complete

  • Tender for Design

    November 2021

    Complete

  • Schematic Design endorsed by Council

    2 May 2022

    Complete

  • Detail design and documentation

    May 2022 - April 2023

    In progress

  • Tender for construction

    May - June 2023

    Scheduled

  • Contract awarded

    July - August 2023

    Scheduled

  • Construction works

    Expected to commence September 2023 (date to be confirmed)

    Scheduled

  • Centre to re-open

    Late 2024 (date to be confirmed)

    Scheduled