Skip to Content

Marian Road Roundabout and Drainage Upgrade

The Marian Road Roundabout and Drainage Upgrade will benefit the community by addressing and reducing the impacts of flooding and helping to protect residents, their homes and property.

Overview

Google Map of Marian Rd, Glynde SA 5070

Cost: $600,000.00

Works for the Marian Road Roundabout and Drainage Upgrade Project include:

  • reconstruction of the Marian Road and Hampden Street roundabout
  • construction of a new incorporated drainage network
  • water sensitive urban design
  • upgrades to the existing roundabout located at the Marian Road and Avenue Road intersection.   

 

Project background

Marian Road between Glynburn Road and Hampden Street was identified as a high priority area in the Council’s City-wide Floodplain Mapping and Long Term Drainage Program.

As a result, a detailed design was commissioned for the reconstruction of the roundabout and drainage network.

To resolve the excessive surface runoff and flooding issues, the works involve the reconstruction and re-alignment of the Marian Road Roundabout, incorporating a new drainage network and water sensitive urban design.

Project details

MLEI Design Consultants were engaged by Council to undertake a detailed design for the project.

The design incorporates water sensitive urban design to capture and re-distribute surface runoff directly into localised rain gardens and treenet inlets. 

The project is scheduled to commence in June 2021 and is scheduled to be completed in September 2021.

Works for this project include:

  • reconstruction of Marian Road/Hampden Street roundabout
  • pavement reconstruction
  • installation of new drainage network
  • construction of raingardens and landscaping works
  • upgrades to existing Marian Road/Avenue Road roundabout.

Marian Road Roundabout & Drainage Upgrade timeline

  • April 2020

    Completed

    Marian Road Roundabout and Drainage Upgrade Detailed Design

  • November 2020

    Completed

    Marian Road Roundabout and Drainage Upgrade Tender released

  • February 2021

    Completed

    Camco SA Pty Ltd appointed as the contractor to construct the Marian Road Roundabout & Drainage Upgrade.

  • June 2021

    In progress

    Construction works

  • October 2021

    Scheduled

    Project to be completed

Project management

City of Norwood Payneham & St Peters

Design

Detailed Design – MLEI Consulting Engineers

Landscape Design – City of Norwood Payneham & St Peters

Main contractor

Camco (SA) Pty Ltd

Contact administration

City of Norwood Payneham & St Peters

Contact

Council’s Project Officer – Civil
Michael Moshos
E: mmoshos@npsp.sa.gov.au
T: 08 8366 4571