Timeline
-
Investigation into road safety improvements at the intersection
May – August 2023Complete
-
Funding application to the Australian Government for Black Spot program
October 2023Complete
-
Awarded funding under the Australian Government’s Black Spot Program
July 2024Complete
-
Council endorsement and acceptance of the funding deed
September 2024Complete
-
Detailed design
August 2025Complete
-
Tender open
September 2025Complete
-
Tender closed
October 2025Complete
-
Contract award
December 2025Complete
-
Construction – Stage 1
Early March – mid-AprilIn progress
-
Construction – Stage 2
Late March – late AprilScheduled
-
Construction – Stage 3
Mid-April – early MayScheduled
-
Construction – Stage 4
Mid-April – early MayScheduled
-
Completion
June 2026Scheduled
Latest News
We are pleased to advise that Council’s contractor, Camco SA, has commenced works onsite.
Camco SA has established their site compound on the eastern side of Giles Street and works will generally be undertaken Monday to Friday, from 7am to 5pm.
Stage 1 works, at the intersection of Kensington Road and Giles Street, are scheduled to be delivered over approximately six weeks (weather permitting). These works include the removal and replacement of drainage infrastructure, kerb and footpath, to facilitate the minor widening of Kensington Road.
Traffic and speed restrictions will be in place to maintain worker and public safety, and we ask the community to allow a little extra time when travelling through this area and always observe onsite signage.
We appreciate your cooperation and understanding as we complete these important works.
