Timeline
-
Concept design endorsed by Council
3 May 2021Complete
-
Schematic Design endorsed by Council
2 May 2022Complete
-
Detail design and documentation
May 2022 - July 2023Complete
-
Tender for construction
August - December 2023Complete
-
Contract awarded to Badge Constructions
25 January 2024Complete
-
Construction works
February 2024 - Late 2026In progress
-
New Centre open to the public
Late 2026 (date to be confirmed)Scheduled
Latest News
To date, the following works have been completed:
> 25m and 20m indoor pools have been filled with water
> building fit out is nearing completion
> 50m pool shade structure complete
> installation of zero-depth waterplay equipment is underway
> waterslide foundations complete.
Next stages include filling the 50m pool, installation of the zero-depth waterplay area shade structure, installation of the waterslide tower & waterslide and landscaping.
To date, the following works have been completed:
Pool Hall
> timber ceiling complete
> 25m pool tiling complete
Pavilion
> structural steel & framing complete
External Works
> 50m pool wall tiling complete
> zero-depth waterplay piling complete
Next stage include amenities tiling, external brickwork, shade structure for the 50m outdoor pool and the Waterslide installation.
To date, the following works have been completed:
> the 50m outdoor pool, and
> the Pool Hall building with the indoor 25m and 20m pools are almost finished.
To date, the following works have been completed:
> demolition of the former buildings, pools and associated infrastructure
> upgrades to the sewer main and water connections
> earthworks and soil contamination management
> concrete pours for the Learn to Swim and 25 metre pools
> installation of precast walls along the OG Road frontage
Next stages include construction of the pool hall building, concrete pours for the 50metre outdoor pool and installation of a new electrical transformer.