Timeline
-
Concept design endorsed by Council
3 May 2021Complete
-
Schematic Design endorsed by Council
2 May 2022Complete
-
Detail design and documentation
May 2022 - July 2023Complete
-
Tender for construction
August - December 2023Complete
-
Contract awarded to Badge Constructions
25 January 2024Complete
-
Construction works
February 2024 - Early 2026In progress
-
New Centre open to the public
Early 2026 (date to be confirmed)Scheduled
Latest News
To date, the following works have been completed:
Pool Hall
> Timber ceiling complete
> 25m pool tiling complete
Pavilion
> Structural steel & framing complete
External Works
> 50m pool wall tiling complete
> Zero Depth Play piling complete
Next stage include amenities tiling, external brickwork, shade structure for the 50m outdoor pool and the Waterslide installation.
To date, the following works have been completed:
> the 50m outdoor pool, and
> the Pool Hall building with the indoor 25m and learn to swim pools are almost finished.
To date, the following works have been completed:
> demolition of the former buildings, pools and associated infrastructure
> upgrades to the sewer main and water connections
> earthworks and soil contamination management
> concrete pours for the Learn to Swim and 25 metre pools
> installation of precast walls along the OG Road frontage
Next stages include construction of the pool hall building, concrete pours for the 50metre outdoor pool and installation of a new electrical transformer.