Timeline
-
Design complete
March 2026Complete
-
Contractor procurement
March 2026Complete
-
Construction to commence
June 2026In progress
-
Construction complete
December 2026Scheduled
Latest News
Works get underway:
Works commenced on the final stage of the Trinity Valley Drainage Upgrade program in early June 2026.
The first phase of works is currently underway to upgrade stormwater drainage infrastructure in Frederick Street and Ford Street. Traffic restrictions will be in place whilst these works are completed to maintain public and worker safety. Please continue to observe onsite signage.
The establishment of the site compound and works area in Cruickshank Reserve has been completed, including installation of temporary construction fencing. Pedestrian access will be maintained to the St Peters Tennis Club and the playground via the existing path adjacent the courts.
What’s happening in July?
Ford and Frederick Streets:
Work will continue to construct new pit and pipes as part of the drainage upgrade. Residents whose driveway access will be impacted have been contacted and our site team will continue to provide updates on the timing of these works to ensure residents can best prepare.
Site investigations — Clifton Street:
Road materials testing and verification of underground services in Clifton Street, between Augusta Street and the eastern end of Cruickshank Reserve are planned for Monday 13 July and Tuesday 14 July 2026, between 7am and 5pm.
Ground samples will be collected by drilling small sections in the roadway and removing a small section of materials for analysis. Where underground services are located, the position will be verified using hydro excavation.
The investigation works may cause short term noise disruption and will require traffic restrictions to maintain safety. Clifton Street will be reduced to one lane for east bound traffic during the day, with traffic movements returning to normal overnight. The left-hand turn from Clifton Street into Phillis Street will be open throughout this period.
Cruickshank Reserve:
Earthworks will commence to prepare for the installation of underground detention tanks and relocation of existing electrical infrastructure will be completed to align with the final layout for the reserve.