Timeline
-
Design complete
March 2026Complete
-
Contractor procurement
March 2026Complete
-
Construction
June 2026In progress
-
Construction complete
Early December 2026Scheduled
Latest News
Major milestones reached:
A significant milestone was reached on 5 and 6 of August 2026, with the first delivery of the StormTrap detention units to site.
These precast concrete units were delivered and positioned on the base slab in Cruickshank Reserve to form part of the detention storage tank.
The stormwater and civil works on Ford Street were completed in August, with the Ford Street and Clifton Street intersection now reopened to traffic.
What's happening in September?
The final phases of the project will be undertaken in Clifton Street, Phillis Street and Mayfair Street.
Clifton Street – Phase 4B:
When: Monday 17 August to early October 2026
Clifton Street will be closed to through traffic between Mayfair Street and Phillis Street. Local access will be maintained.
The westbound lane and left turn from Clifton Street into Phillis Street will remain open.
Mayfair Street – Phase 3:
When: 2 September to end of October 2026
Mayfair Street will be closed to through traffic. Local traffic will be permitted, with some impacts to driveway access.
Clifton Street / Phillis Street roundabout – Phase 4B:
When: 1 October to early November 2026
The intersection of Phillis Street and Clifton Street will be closed while new stormwater infrastructure is constructed and the roundabout upgrade is completed.
Traffic management:
Local detours will be in place. Residents and motorists are asked to allow more time when travelling through the area.
We apologise for any inconvenience and thank the community for their patience while we complete these important works.
Access to the Maylands Hotel will be available throughout the construction period via the Phillis Street carpark entrance.
Frederick Street:
The stormwater and civil works on Frederick Street, including the reconstruction of the Frederick Street and Clifton Street roundabout, are nearing completion.
The road will be reopened to traffic in early September.
Cruickshank Reserve:
Earthworks are continuing to backfill around the installed underground detention units and prepare the northern portion of the Reserve for installation of the remaining detention units.
Works get underway:
Works commenced on the final stage of the Trinity Valley Drainage Upgrade program in early June 2026.
The first phase of works is currently underway to upgrade stormwater drainage infrastructure in Frederick Street and Ford Street. Traffic restrictions will be in place whilst these works are completed to maintain public and worker safety. Please continue to observe onsite signage.
The establishment of the site compound and works area in Cruickshank Reserve has been completed, including installation of temporary construction fencing. Pedestrian access will be maintained to the St Peters Tennis Club and the playground via the existing path adjacent the courts.
What’s happening in July?
Ford and Frederick Streets:
Work will continue to construct new pit and pipes as part of the drainage upgrade. Residents whose driveway access will be impacted have been contacted and our site team will continue to provide updates on the timing of these works to ensure residents can best prepare.
Site investigations — Clifton Street:
Road materials testing and verification of underground services in Clifton Street, between Augusta Street and the eastern end of Cruickshank Reserve are planned for Monday 13 July and Tuesday 14 July 2026, between 7am and 5pm.
Ground samples will be collected by drilling small sections in the roadway and removing a small section of materials for analysis. Where underground services are located, the position will be verified using hydro excavation.
The investigation works may cause short term noise disruption and will require traffic restrictions to maintain safety. Clifton Street will be reduced to one lane for east bound traffic during the day, with traffic movements returning to normal overnight. The left-hand turn from Clifton Street into Phillis Street will be open throughout this period.
Cruickshank Reserve:
Earthworks will commence to prepare for the installation of underground detention tanks and relocation of existing electrical infrastructure will be completed to align with the final layout for the reserve.